Frick Coalescer Installation guide

  • I have reviewed the Installation Bulletin for the Frick Coalescer models 531B0104H01, 531B0104H03 and 531B0104H05. This document provides crucial instructions for the correct installation, including orientation and torque specifications. I'm ready to answer any questions you might have about these coalescing elements.
  • What is the correct orientation of the coalescing element?
    What is the required mounting torque for the element?
    Can this element be used in vertical applications?
Installing the coalescing element
1. Orientate the 531B0104H0_ Coalescing
Element with the DRAIN DOWN tag on the
bottom, at the 6 o’clock position, to ensure
the internal bridge is correctly oriented.
Failure to orient correctly may result in ow
bypassing the coalescing element.
2. The required mounting torque is 21 ftlb.
Excessive torque may damage the element
and result in oil carryover.
Johnson Controls
100 CV Avenue
Waynesboro, PA 17268
Phone: 717-762-2121 • FAX: 717-762-8624
www.johnsoncontrols.com/frick
Form 160.120-IB (2021-09)
Supersedes: 160.120-IB (2020-10)
Subject to change without notice
Published in USA • 09/21 PDF
© 2021 Johnson Controls - All Rights Reserved
NOTICE
These elements are only for horizontal applications
.
Original equipment
For Genuine Frick® Replacement Parts, contact:
Johnson Controls Inc.,
Frick Parts Center,
9104-D Yellow Brick Road,
Baltimore MD 21237
Phone: (800) 336-7264
CAUTION
Incorrect drain position decreases performance.
Form 160.120-IB (SEP 2021)
Installation Bulletin
File: Service Manual - Section 070
Replaces: 160.120-IB (OCT 2020)
Dist: 3, 3a, 3b, 3c
Part No: 531B0104H01, 531B0104H03,
and 531B0104H05
Description: High-efciency, high-performance
coalescer element
Frick Coalescer
Figure 1: Coalescing element
Note: The part number, torque value, and date code are shown on the side of coalescer
/