Hadco i25 Inground, i1.5 Inground Composite Concrete Pour, i15 Inground, i35 Inground Install Instructions

  • Hello! I've reviewed the installation instructions for the Philips CPS series concrete pour kits, including the CPS15, CPS25, and CPS35 models. This document provides details on how to properly install these stainless steel kits for inground fixtures, ensuring they are anchored securely and flush with the concrete. It also highlights the importance of a proper sand/gravel foundation for drainage. I'm ready to answer any questions you have about the installation process or the features of these concrete pour kits.
  • What material is the concrete pour kit made of?
    What is included with the concrete pour kit?
    What is the minimum depth for the sand/gravel foundation?
    Can the position of the concrete pour kit be adjusted after the concrete is poured?
RE-BAR (BY OTHERS)
ANCHOR FIXTURE WITH
DEPTH.
EYEBOLTS (PROVIDED)
CONCRETE
CONDUIT RUN
DRAINGE, 3" MIN
SAND/GRAVEL
FOUNDATION FOR
POUR CONCRETE FLUSH WITH
TOP OF CONCRETE POUR KIT.
FIXTURE "X" DIM "Y" DIM
i1.5 4" 8"
i2.5 16" 20"
i3.5 16" 20"
YX
100 Craftway Dr.
CONCRETE POUR KIT
32001697, revision D
Littlestown, Pennsylvania 17340-0128
Phone: 717-359-3171
INSTALLATION INSTRUCTIONS:
CPS15 / CPS25 / CPS35 - STAINLESS STEEL
page 1 of 2
qualified electricians with proper grounding in accordance with National Electrical Code (NEC).
can occur if electrical equipment is not installed properly. This equipment should only be installed by
Improper installation and/or utilization may void manufacturer's warranty.
3. Do not install fixture within 10 feet (3 meters) of a pool, spa or fountain.
periods of time.
2. The fixture should not be installed in low lying areas or where water may accumulate and stand for long
occur that are not addressed by these instructions, contact your distributor or Sales Representative for assistance.
CAUTION:
1. WARNING: Do not remove labels from this pour kit. Carefully read all warnings and installation procedures
before continuing installation. Failure to follow these instructions will void warranty. DANGER-Fatal shock
READ THESE INSTRUCTIONS CAREFULLY BEFORE USING THIS CONCRETE POUR KIT.
These instructions do not purport to cover all details or variations in equipment, nor to provide for every possible
contingency related to installation, operation, maintenance, or mounting situation. Should specific problems
Figure 1: CPS25 POUR KIT WITH I25 FIXTURE SHOWN. INGROUND FIXTURES SOLD SEPERATELY.
STEP 3: Secure Concrete Pour Kit in final position with re-bar and other anchoring devices (not provided) via the
The fixture only sits one way inside the Concrete Pour Kit, see Figure 2.
INSTALLATION
Note: eyebolts (supplied).
foundation so that the concrete level when poured will be flush with the top of the kit.
STEP 1: Excavate soil for Concrete Pour Kit placement and conduit runs. Contour the hole to the shape of the
Concrete Pour Kit, making sure the kit is placed on a 3" minimum bed of sand / gravel with the soil below.
Allow 3" minimum around the kit for concrete to settle.
STEP 2: To ensure proper drainage, prepare the sand / gravel foundation. The height of the Concrete Pour Kit varies
between fixtures (see chart on page 1) and allows space below the fixture. Adjust the depth of the
STEP 4: Run sufficient conduit so that it will reach the junction box which is near the top of the fixture, see Figure 1.
STEP 5: Pour concrete flush with top of Concrete Pour Kit. Remember, Concrete Pour Kit position cannot be
altered after pouring concrete.
STEP 6: Once concrete has set and is completely cured, complete fixture installation according to instruction
sheet provided with fixture.
page 2 of 2
32001697, revision D
Assembled View
JUNCTION BOX COMPARTMENT
JUNCTION BOX
COMPARTMENT
MOUNTING SCREWS
(PROVIDED)
(3PLACES)
RESTS ON UPPER LEDGES.
(3 PLACES)
MAIN HOUSING RESTS
ON LOWER LEDGES
MAIN HOUSING
Figure 2: FIXTURE POSITION WITHIN CONCRETE POUR KIT.
/