HomePlace Structures LS1016, LS1016F, LS1020, LS1020F Operating instructions

  • Hello! I've reviewed the Assembly Manual for the Suncast Studio Garden Building, including the 10 x 16 and 10 x 20 models. This document provides detailed instructions for assembling the building from the ground up, covering everything from the floor and walls to the roof and trim. I'm ready to answer your questions about the assembly process, the components, required materials or any of the optional features like the cupola or flower boxes.
  • What tools are needed for assembly?
    What additional materials are required?
    What should I do if the package is damaged upon arrival?
    What is the importance of a level site?
Studio Garden Building
Assembly Manual
© Suncast Corporation
Toll Free: 866.768.8465
Hours: 9-5 Monday-Friday EST





























 






 


 

 
















Please read through the entire manual before starting!
Note: It is very important that you have a level site for the garden building.
When using tools and ladders always follow manufacturers recommended safety guidelines!
Tools Needed:
Level
Screw Gun
Hammer
Tape Measure
Skill Saw
Speed Square
Chalk Line
Pencil
5/16” Drill Bit
Tin Snips
Caulking Gun
Other Items Needed:
Approximately 5 gallons of paint
Approximately 12 Bundles of shingles
Heavy duty Silicone Caulk/Sealer
Studio Guesthouse
Assembly Manual
revised 2/2/06
© Suncast Corporation
When your kit arrives, it should look like this.
Inspect the package for any damage that may
have occurred during shipping, dented cor-
ners, punctured plastic, etc. If the package is
damaged, alert HomePlace Structures imme-
diately at 866.768.8465.
Hardware & Fasteners
3”16 Penny Nails
Color Code: Fluorescent Green
Page 3
2-1/2” 7 Penny Nails
Color Code: Pink
2” 6 Penny Nails
Color Code: Orange
2” Trim Nails
Color Code: Fluorescent Yellow
1-1/2” Red Shutter Screws
Color Code: Dark Blue
2” Black Hinge Screw
Color Code: Black
1” Pan Head Window Screws
Color Code: Light Blue
1” Roofing Nails
Color Code: Purple
1-1/2” White Washer Head
Flower Box Screw
Color Code: Dark Green
The following fasteners are included with your kit. However, you will find the assembly process to pro-
ceed much faster when using air powered tools and fasteners. When replacing hand fasteners with air
powered fasteners, always use a fastener equivelant.
© Suncast Corporation
Page 4
10 x 16 Studio
10 x 20 Studio
Page 5
Optional Floor Assembly
Step 1: Cut open floor kit, cut metal bands, and remove top plywood sheet as shown.
Your floor kit should include all of the following parts:
Page 6
© Suncast Corporation
See drawings on previous page for measurements.
If you did not purchase the optional floor, please proceed to page 8.
Pressure Treated 2”x4”:
17 - 8'
13 - 17”
OSB pieces:
24 - 3-1/2" x 23-1/2"
5/8” Plywood Flooring
3 - 4’x8’ sheets, 2 - 4'x4' sheets
2 - 20"x8'
Note: The unit assembled for this manual was 10’x16’. This manual
is designed to help assemble a 10’x16’ or 10’x20’ Studio. If you have
purchased a 10’x20’ unit, please not that the pictures for some steps
will appear different from. Please refer to the included drawings for your
specific unit.
Step 2: Layout four 8’ pressure treated 2”x4” floor plates, mark off for floor joists at 16” on center and
square as shown.
Step 3: Layout floor as shown.
Note: See attached drawing for
measurements.
Step 9: Fasten plywood sections to floor joists using penny 7 p. 2-1/4” galvanized nails spaced 8” apart.
Note: It is important to align plywood properly at edges.
Step 4: Attach short floor joists to
long floor joists using using 6 p. 2”
nail and OSB pcs, keeping all pieces
flush at top.
Step 5: Attach floor joists
together at appropriate mea-
surements using 2-16 p. 3”
nails per joist
Step 6: Attach outside band-
board joists together as shown.
Step 7: Make sure floor is square.
Floor is square when diaganol mea-
surements are equal.
Step 8: Layout plywood floor
sections as shown.
Tip: It is important to level
floor before proceeding to
next page.
page 7
Bottom Wall Plate Layout
for Units without floor
Step 10: Cut open large package and remove packing materials repeating step 1.
Step 11: Remove top layer of
4’x8’ OSB roof sheeting and
place to the side.
Note: Unpack kit all the way
down to layer 5.
Note: If you purchased the optional floor, please proceed to back wall layout and assembly page.
Step 12: Remove next layer of
kit and set aside.
Step 13: Remove screws from
4’-2”x4” double wall plates
and set aside.
Step 14: Remove all remain-
ing pieces (excluding pressure
treat 2”x4” bottom wall plates)
Step 15: Measure a square
pad at 116”x192” and snap
lines as shown. Make sure
layout is square, see step 19.
Note: The measurement for
a 10’x20’ unit is 116”x240”.
Wall Plate 2”x4”Material List:
10 - 8 6 - 25
4 - 4 6 - 7
page 8 © Suncast Corporation
Step 16: Layout 6’ pressure treated bottom plates as shown.
Step 17: Mark and cut bottom plates to fit.
See next step
Step 18: It is recommended
put a layer of clear silicone
sealer under bottom plates.
Step 19: Make sure bottom
plate layout is square. It is
square when diaganol mea-
surements are equal.
Step 20: Fasten bottom plates
to surface using concrete
screws, tapcons, or fastener
equivelant.
Bottom plate layout is com-
plete.
page 9
© Suncast Corporation
10 x 16 Back Wall Layout
Page 10
10 x 20 Back Wall Layout
Page 11
Back Wall Layout & Assembly
page 12
© Suncast Corporation
Step 21: Layout top (top plate is a double wall plate) and bottom wall plates, measure and mark at 16”
on center as shown.
Step 22: Layout 79”-2”x4” wall studs and fasten to top and bottom plates at marks using 2 16p 3” nails
per stud as shown.
Note: It is very important align top of studs flush with top of wall plate.
See drawings on previous page for measurements.
Step 23: Remove four 4’x85” sheets siding and layout on wall as shown.
Step 24: Start siding with over-
lap at corner with 1” overhang
at end end of wall.
Step 28: Mark and cut off
excess siding as shown.
Step 25: Siding edge should
center on wall stud as shown.
Step 27: Install next siding piece as shown, keeping groove reveal
consistent with other openings on sheet. Repeat to end of wall.
Step 29: Lift and set wall as
shown.
Step 30: Fasten wall to floor
using 16p 3” nails every 8”.
Make sure edges are flush.
Step 31: Fasten siding to floor
using 7p 2-1/4” galvanized
penny nails every 8”.
Siding should be 1-1/2”
down past top of floor.
Step 26: Fasten siding to
walls using 7p 2-1/4” galva-
nized penny nails every 8”.
page 13
10 x 16 Front Wall Framing
Page 14
10 x 20 Front Wall Framing
Page 15
Front Wall Layout & Assembly
Step 32: Layout top and bot-
tom wall plates as shown.
Step 34: Use square to mark
top and bottom plates.
Step 33: Mark off wall using
measurements shown in draw-
ing.
Step 35: Layout wall studs
aligning studs with marks on
wall plates.
Step 36: Leave out one 8”
block at top of door, this will
be installed when applying
siding.
See drawings on previous page for measurements.
page 16
© Suncast Corporation
Step 37: Nail wall together using 16p 3” nails as shown.
Step 38: Window Layout
should look like this.
Step 41: Begin with 4’x85” sid-
ing pieces on either side of
door, keeping 1/2” away from
edge of 2x4. Nail 4’x85” across
top only and only one nail at
bottom doorway corner of
siding piece.
Note: Left side of door
should have siding underlap.
Note: Right side of door
should have siding overlap.
Step 39: The wall is now ready
for siding installation.
Step 40: Layout front siding
pieces as shown.
Step 43: Before nailing rest of
siding, make sure that door
opening is square. Door is
square when corner to corner
diaganol measurements are
equal.
Siding Measurements:
2 - 1’x85”, 2 - 4’x85”
2 - 11-3/4”x4’ (for top of door)
1/2”
Reveal
3/4”
Reveal
One Nail
Here
Step 42: Install 11-3/4”x4’ sid-
ing piece at top of door way
- nail across top only.
page 17
© Suncast Corporation
Step 44: Install remaining door
header stud to center on siding
piece splice.
Step 46: Cut siding piece to fit using mark and install as shown.
Step 48: Lift and set wall
repeating steps from back wall.
Step 51: Use nails to snap 4
lines to mark window outline.
Step 45: Take remaining 11-3/4”x4’ door header siding and mark
piece as shown.
Step 49: Fasten wall bottom
plate to floor and siding to floor
repeating previous steps.
Step 50: Put a nail in each
corner of window (4 total) and
out through siding.
Step 52: Use a skill saw to cut
out window opening.
Front wall is complete.
Note: Remove nails prior to
cutting
Step 47: Install remaining sid-
ing pieces.
page 18
10 x 16 and 10 x 20 Side Wall Layout with Window
Page 19
/